- Getting Started with Test Suite
- Studio
- Orchestrator
- Testing robots
- Test Manager
Xray for Jira
The Xray Test Management for Jira integration provides an alternative to managing your tests using the Test Manager. To take advantage of this, you need to install the Jira connector and complete the integration by configuring a new connection in the Test Manager.
To connect your Test Manager instance to an XRay project follow these procedures:
- Items synchronized from Xray for Jira to Test Manager are read-only except for attachments, object labels and test case links.
- Defects are synchronized from test executions in Test Manager to Xray for Jira.
The direction of data transfer and corresponding objects are listed in the following table:
Xray for Jira |
Direction |
UiPath Test Manager |
---|---|---|
Requirements |
→ |
Requirements |
Test cases |
→ |
Test cases |
Defect |
← |
Defects |
- Jira Server account
- UiPath® Test Manager for Jira Server and Jira Data Center - required for Xray for Jira Server and Jira Data Center integration.
- UiPath® Test Manager for Jira Cloud - required for Xray for Jira Cloud integration.
- Log in to Jira as an administrator.
- Navigate to Settings > Manage Apps.
- Go to Find new apps.
- Use the search bar to find UiPath® Test Manager for Jira.
- Click Install to add the app to Jira.
Paragraph
, named UiPath Automation
to associate it with screens in Xray for Jira. This step is needed so you can view test case automation information in Xray
for Jira.
For more information, see Custom Fields and Screen Configuration.
- Log in to the Test Manager as an administrator.
- Open your project.
- Click the Settings button to open Project Settings.
- In the Integration list, click an Xray connection to expand the panel.
- Click Edit to configure the connection.
- Click Save to confirm.
Deleting the connection removes all associated requirements and test cases.
- Log in to the Test Manager as an administrator.
- Open your project.
- Click the Settings button to open Project Settings.
- In the Integration list, click an Xray connection to expand the panel.
- Click Delete to remove the connection.
- Click Ok to confirm.
The tests executed through the Orchestrator propagate the results to Xray. For more information on managing tests using Xray, see the Xray Documentation Home.
- Test cases edited in the Test Manager are not synchronized with Xray. Conversely, changes made to test cases in Xray are reflected in the Test Manager.
Related articles